19.02.2020

Silver Tower

Due to the Up & Down construction, it was necessary to strengthen the central core of the tower between the new foundations (on level -8) and the rest of the tower. We used 100 hydraulic jacks that applied pressure of 580 bars and cleared a space of 28 mm to be filled. Once this operation completed, construction can continue from the 28th to the 32nd floor.